TM 9-2350-222-20-1-4
SHIFT LINKAGE ADJUSTMENT (Sheet 5 of 20)
Using 9/16 inch wrench, install screw (S)
19.
through link (V) and shifting rod bearing end
(u).
Using torque wrench and crowfoot wrench,
20.
tighten jamnuts (Q) and (R) to 15-20 lb-ft
(20-27 N l m).
Remove locating pin from alinement hole (P).
21.
Using 9/16 inch socket and torque wrench,
22.
tighten screw (S) to 15-20 lb-ft (20-27 N.m)
and go to step 43.
Using 9/16 inch wrench, adjust shifting rod
23.
bearing end (U) clockwise until shifting rod
(T) is past hole (W).
Using 9/16 inch wrench, remove screw (Y).
24.
Using 9/16 inch wrench, install screw (S)
25.
through link (V) and shifting rod bearing end
(u).
Using crowfoot and torque wrenches,
26.
tighten jamnut (Q) to 15-20 lb-ft
(20-27 N l m).
Using 9/16 inch socket and torque wrench,
27.
tighten screw (S) to 15-20 lb-ft (20-27 N.m).
Go on to Sheet 6
TA253365
11-6 Change 1