TM 9-2350-222-20-1-4
Bilge Pump/Gas Particulate Switch Cable Assembly Replacement (Sheet 1 of 2)
PROCEDURE INDEX
PAGE
PROCEDURE
Removal
Installation
SUPPLIES: Silicone compound (Item 32, Appendix D)
PRELIMINARY PROCEDURE:
REMOVAL:
Remove lead from bilge pump and gas particulate circuit breaker (A).
1.
Remove lead from bilge pump switch (B).
2.
Remove lead from gas particulate switch (C).
3.
4.
Remove cable assembly (D).
Go on to Sheet 2
TA139672
10-116