TM 9-2350-222-20- 1-3
POWERPLANT REPLACEMENT (2D ENGINE) (Sheet 10 of 23)
CAUTION
Check all disconnected rod and
line ends, hoses, and cables to
make sure they will be out of the
way during powerplant removal.
32.
Connect hoist hook to engine and
transmission sling. Make sure hoist
hook is put through hole used to lift
powerplant.
33.
Using hoist with engine and trans-
mission sling, position sling over
powerplant so T-end is to front of
vehicle.
34.
Attach four cable hooks of engine
and transmission sling to four lifting
ends are toward outside of vehicle.
35.
Position personnel to guide powerplant as
it is hoisted out of vehicle.
Go on to Sheet 11
Change 4
5-34