TM 9-2350-222-20-1-3
EXHAUST PIPE (LEFT SIDE) REPLACEMENT (Sheet 3 of 4)
INSTALLATION:
Position packing (A) and clamp (B) onto pipe (C) and, using flat-tip screwdriver, tighten screw on
1.
clamp (B), securing packing to pipe (C).
2.
Check insulation halves (D) and all attaching hardware for damage. Replace if necessary.
Position insulation halves (D) onto exhaust
pipe (C).
4.
Using wrench and cross-tip screwdriver, install 14 screws (E), each with two flat washers (F), one
new lockwasher (G), and one nut (H) to hold insulation halves (D) to exhaust pipe (C).
5.
Position new gasket (J) onto turbosupercharger housing (K).
6.
Slide exhaust pipe extension (L) into tube (M)
as far as it will go.
7.
Position exhaust pipe (C) with installed
insulation halves (D) onto turbosupercharger
housing (K). Make sure exhaust port (N) is
pointing up.