TM 9-2350-222-20-1-4
TRACK SUPPORT ROLLER REPLACEMENT (Sheet 1 of 11)
PROCEDURE INDEX
PROCEDURE
PAGE
Removal
Installation
9/16 in. socket with 1/2 in. drive
Pliers
2-1/2 in. socket with 3/4 in. drive
3/16 in. alining punch
Hydraulic jack
3/8 in. punch
Hammer
1/2 in. rod
Flat-tip screwdriver
Straight punch 3/4 in. dia. 10 in. long
SPECIAL TOOLS: Slide hammer puller (Item 12, Chapter 3, Section I)
Spanner wrench (Item 27, Chapter 3, Section I)
Oil seal replacer (Item 21, Chapter 3, Section I)
FABRICATED TOOLS:
Mechanical puller (Figure F-6, Appendix F)
SUPPLIES: Gaskets (73641 15) (2 required)
Grease (Item 36, Appendix D)
Rags (Item 65, Appendix D)
Spring pins
Seals
Nut lock
Cotter pin
Wooden planks 2 in. by 6 in. by 4 ft. (or metal plates) (2 required).
Wooden safety block 2 in. by 6 in. by 2 ft.
PERSONNEL: Two
REFERENCES:
TM 9-2350-222-10
LO 9-2350-222-12
TRACK SUPPORT ROLLERS
Go on to Sheet 2
TA253471
14-34
Change 1