TM 9-2350-222-20-2-3-2
HOLD-OPEN MECHANISM INSTALLATION PROCEDURE (CONT)
30-5.
FRAME 1
STEP
PROCEDURE
1.
Open hatch (1) about half way.
2.
Line up hold-open mechanism (2) with mounting holes on hatch (l).
3.
Put sealing compound on screw (3) and screw (4) (JPG).
4.
Using socket wrench, install screw (3) lockwasher (3.1), and shims (5).
5.
Using socket wrench, install screw (4), lockwasher (4.1) and shims (5).
6.
Move hatch (1) to locked position. Check for smooth operation of hold-open mechanism (2).
7.
Using feeler gauge, check gap between cam (6) and cover (7). Gap should be not more than 0.015 inch
(JPG). If gap is more than 0.015 inch, shims (5) will have to be added or removed. Hold-open
mechanism (2) should work easily without binding.
GO TO FRAME 2
Para 30-5 Cont
Change 1 30-15