TM 9-2350-222-20-1-3
MANIFOLD HEATER OPERATIONAL CHECK (Sheet 1 of 2)
SPECIAL TOOLS: Ground hop kit (Item 30, Chapter 3, Section I)
PERSONNEL: TWO
PRELIMINARY PROCEDURE:
OPERATIONAL CHECK:
NOTE
This procedure applies to manifold heaters on both 2A and 2D
Make this check after any part of manifold
heater system is replaced.
I t requires two persons to
complete.
1.
2.
Station one person on side of engine that maintenance was performed, with one hand on intake
manifold heater tube (A).
2A ENGINE SHOWN, 2D LOCATION
IS THE SAME
Go on to Sheet 2
TA148926
7-363